Wednesday, 7 December 2011

Start a Neck – Ties Making Unit

         
(244)  Start a Neck – Ties Making Unit
   




Ties are considered as item of fashion. Ties has been finding exceptionally good acceptance among the sales representatives, doctors, CEO's, Engineers, Hotel servants and others such as college and school students. Shirts worn without ties are considered as incomplete. Wearing of ties improves one's personality and respect. Ties are classified into two types, which are bow ties and neck ties. The former one are generally worn by hotel waiters whereas the later are worn by people mentioned above.
Ties are made from various types of fabrics and most popular fabrics that are used for the manufacture of ties are cotton, viscose, silk fabrics and their blends. Manufacturing of ties is very easy and anyone knowing tailoring and managing a unit can venture into this industry. The raw material and machinery required for the manufacture of ties are abundantly available. In this report, an attempt has been made to provide sufficient information for setting up of tie manufacturing units.
Market Potential
In recent years almost all the countries in the world are witnessing lot of changes in life style of people. Present life style is witnessing very fast changes in wearing fashion garments. The demand for fashion garments is very huge due to shifting of wearing fashion garments from elite people to common persons. Among various fashion garments, tie occupies an important place. There are very less number of units engaged in the manufacture of ties and as such demand and supply gap is getting wider. Tie have its own market demand from various market segments. Main customers for ties are Doctors, CEOs, Sales representatives, waiters in star hotels, reception counters and executives.
Basis and Presumptions
1. This project is based on double shift basis and 300 working days in a year.
2. The Building is considered of own.
3. The cost of machinery and equipments/materials indicated refers to particular make and approximately to those prevailing at the time of preparation of this project.
4. The cost of installation and electrification is taken @ 10% of cost of machinery and equipment.
5. Non refundable deposits, project report, cost, trial production, security deposits with electricity board are classified under preoperative expenses.
6. Depreciation has been considered:

(a) on plant and machinery @ 10%
(b) on office furniture & fixtures @ 20%
7. Interest on capital investment has been taken @13% per annum on borrowing amount.
8. Minimum 25% of total investment is required as margin money.
Implementation Schedule
Sl. No.ActivityPeriod
1.Selection of site/working shed1 month
2.Preparation of feasibility report1 month
3.Registration with commissioner of Industries/DIC1 month
4.Arrangement of finance (term loan and working capital)3 months
5.Procurement of machinery and equipment1 month
6.Plant erection and electrification2 weeks
7.Arrangement of raw material including packaging material1 month
8.Miscellaneous works like power/water connection etc.2 months
Note: Considering that some of the above activities may be overlapping, the project implementation will take a period of 4 months approximately for starting the production.
Technical Aspects
Process of Manufacture
Before starting the stitching operations, fabrics of required quality are placed on the cutting table in layers and lay mark is prepared on top of the fabric layer and these layers are perfectly cut as per the mark without any distortion in cutting. The panels after cutting are taken out from the table and supplied to the skilled tailors for stitching. After the stitching, ironing is done with the aid of electric iron. Ironing is an important process by which ties are given proper and final shape. Ties are finally checked for any objectionable faults and packed for marketing.
Quality Control and Standards
This product is consumable item and having different designs and colours and its combinations depending upon the demand of the consumers. So standard specifications of appropriate quality is not possible. However, to manufacture better quality, good quality fabrics and other materials are to be used.
Production Capacity (per annum)
 Qty. (pcs)Value (Rs.)
Ties of different sizes2100005250000
Motive Power
Power required to run this industry will be 5 HP.
Pollution Control
This industry does not involve anypollution.
Energy Conservation
Power requirement is very low, even then energy can be saved by proper house keeping.
Financial Aspects
A. Fixed Capital
(i) Land and Building
Land 200sq.mt. @ Rs. 3000p.s.m. Amounting Rs 600000.00
Building Area
Factory shed100 sq. mt.
Store (Raw material)25 sq. mt.
Store (Finished goods)50 sq. mt.
Office etc.25 sq. mt.
Total Covered Area100 sq. mt.
Total Construction Cost @ Rs. 4000/sq.mt.400000.00
Total Investment in land and Building1000000.00
Machinery and Equipments
Sl. No.DescriptionNo.Rate (Rs.)Amount (Rs.)
1.Eastern straight bar cloth cutting machine with motor17000070000
2.Power operated single needle lock sewing machine103203200
3.Electric iron422008800
4.Table and workshop itemsLS1700017000

(iii)Other Fixed Assets(Rs.)
a.Erection and installation9900
b.Office furniture25000
c.Pre-operative expenses25000
 
Total
158900
 Total Fixed Capital1158900
B. Working Capital (per month)
(i) Staff and labour wages
Sl. No.DesignationNos.Rate (Rs.)Amount (Rs.)
1.Manager/Designer180008000
2.Clerk/Typist140004000
 Production Staff   
1Cutting Master2600012000
2.Skilled workers18380068400
3.Helpers8300024000
 
Total
116400
 Perquisites @ 20%23280
 
G. Total
139680
(ii) Raw Material
Sl. No.DescriptionUnitQty.Rate/ Unit (Rs.)Amount (Rs.)
1.Synthetic fabrics of different colours, shades and designMts.300054162000
2.Sewing thread labels of different colours and shadesMts.LS70007000
3.Packing materialsNos.LS2000020000
 
Total
189000

(iii) Utilities(Rs.)
Electricity Bill6000
Water charges500
Total
6500

(iv)Other Contingent Expenses(Rs.)
1Postage/Stationery1000
2Repairs and maintenance800
3Transport /travelling charges1000
4Insurance250
 Misc.2000
 
Total
5050
(v)Total Recurring Expenses (per month)340230
(vi)Total Working Capital (for 2 months)680460
C. Total Capital Investment
1.Land Machinery and equipment1158900
2.Working capital (for 2 months)680460
 
Total
1839360
Machinery Utilisation
Capacity utilisation is considered as 70% of installation capacity.
Financial Analysis
(1) Cost of Production (per year)(Rs.)
Recurring expenses4082760
Depreciation on Building @ 5 %50000
Depreciation on machinery @ 10%15890
Depreciation on Office furniture @20%5000
Interest on total investment @13%239116.8
Total
4392766.8

(2) Turnover (per year)Qty. (pcs)Rate/ (Pc.)Total (Rs.)
Ties of synthetic fabrics210000255250000

(3)Net Profit (per year)857233.2
(4)Net Profit Ratio (Net Profit/ Turnover (per year)19.51
(5)Rate of Return on Investment (Net Profit/Total Capital Investment)46.6
(6) Break-even Point
Fixed Cost(Rs.)
Depreciation on Plant & Machinery office equipment etc20890
Depreciation on Building50000
Interest on capital investment239116.8
40% of wages of staff and labour670464
40% of other expenses23040
Insurance3000
Total
1006510.8



Start a Automobile body (Bus Body) building

      
(243) Start a Automobile body (Bus Body) building
       



Automobile body (Bus Body) building is an important activity. The chasis are supplied by Automobile manufacturers, and body is built by automobile body builders as per the requirements of the customer and specifications of the different State Transport Undertakings.
Market Potential
Bus is used as the most common public transport vehicle in our country. Different State Transport Undertakings are plying their buses for commuting public from one place to another and from one State to another. Apart from these Undertakings, Private Bus Operators, travel agencies etc. are also operating buses on permit basis. With rapid changes in the society, now a days it has become necessary to provide good and efficient service to the public. Also with the rapid industrialisation, public is moving very frequently from one place to another using public transport. Since more and more development in the coming years, it is expected that demand of public transport, private transport and luxury transport in the form of buses will increase in the coming years.
Basis and Presumptions
1.  Working will be for 3 shifts per day of 08 hrs each at minimum 75% working efficiency to achieve the envisaged production capacity.

2. A time period of three years has been considered for achieving the full capacity utilisation after start of commercial production.

3. Labour wages are considered as per the prevailing market rates.

4. Interest on fixed and working capital investment has been calculated at an average rate of 12% per annum.

5. The cost of land and building has been calculated as per the prevailing market prices, and these rates are likely to vary from place to place.
Implementation Schedule
The following activities are to be completed and the approximate time for each activity is as mentioned against each of them:
Sl. No.ActivityPeriod (in Weeks)
1.Selection of product4
2.Selection of Industrial site2
3.Provisional registration2
4.Preparation of project Report2
5.Application for finance and getting Loan sanctioned24
6.Recruitment of man power4
7.Purchase and Installation of machinery14
8.Trial Run1
It is necessary to obtain permanent Registration Certificate from the concerned District Industries Centre after commencement of commercial production.
Technical Aspects

Process of Manufacture
Metal sheets are cleaned and derusted for grease/oil if any. Then sheets are cut to size for forming different parts and these parts are formed on press brake. Now different parts and their subassemblies are fabricated as per their design and size. These parts and subassemblies are fabricated– together to make them a complete bus body. The complete body is painted as per the requirements of the customer. Shower test is carried out for leakage etc.
Production Capacity (per annum)
Quantity:324 Nos.
Value:Rs 13,51,00,000
Motive Power:150 HP (Approx.)
Pollution Control
The manufacturing/fabrication of bus body does not pose any problem for pollution. However, proper ventilation is to be done in shop floor area and painting area. Provision for pollution control equipments has been made in this Project Profile.
Energy Conservation
Suitable energy efficient motors are to be used on proposed machines with provision of recommended shunt capacitors.
Financial Aspects

A. Fixed Capital
(i) Civil costAmt. (In Rs.)
(a) Land 4000 Sq.Mtrs. @ Rs. 3500/ Sq.Mtr.1,40,00,000
(b) Office - 100 Sq. Mtr @ Rs.7500/Sq.mtr.7,50,000
(c) Store –150 Sq. Mtr @Rs.6000/Sq.mtr.9,00,000
(d) Working shed - 2000 Sq. Mtr. @ Rs. 6000/Sq.mtr. bore well and raw water storage, DG set room, security room, laboratory, maintenance room, workers room1,20,00,000
(e) Paint Shop (Preferably Dust Proof) - 100 Sq. Mtr. @ Rs. 7000 per Sq. mtr.7,00,000
(f) Boundary wall, gates, roads inside the premises8,00,000
Cost of land and building = 1,40,00,000 + 1,51,50,0002,91,50,000
(ii) Machinery and Equipments
Sl. No.DescriptionInd./ Imp.Qty.
Total
(In Rs.)
1.Motorised Guillotine Sheet Shearing Machine Capacity 2500×4 mm with 10 HP electric motor and starter etc. also fitted with front and back side gauges, sheet holding devices etcInd.1
9,00,000
2.Power operated Press Brake bending capacity 2440 × 4 mm, 100 Ton with 15 HP Main Motor and 2 HP raw adjustment MotorInd1
11,00,000
3.Suspension type M.I.G. Welding system 250 Amp. along with power source, wire feeder, Torch and flow Calibrated Co2 regulator and Co2 heated with core assembly OPC.Ind.1
2,00,000
4.Gas Welding set with all the Accessories etc.Ind.2
50,000
5.Arc welding machine 300 Amps. 15 kVA Air Cooled complete with all the accessoriesInd.5
2,00,000
6.Air Compressor with painting equipment and accessories for paintingInd.1
2,00,000
7.Different types of power/Air operated tools like Nut runner, drilling gun etc.Ind.L.S.
4,00,000
8.Drilling Machine 1½" capacityInd.2
1,00,000
9.Metal cutting bandsaw for cutting Aluminium sections complete with 2 HP Electric motor and accessoriesInd.1
1,00,000
10.Hoist chain pulley block crane and material handling trolley etc.Ind.L.S.
5,00,000
Testing Equipment and others
1.Shower tester self fabricated (Nozzles to be arranged at different orientations to cover the entire portion of the vehicle)Ind.1
3,00,000
2.Portable digital paint thickness checking equipment (Coating thickness checking)Ind.-
25,000
3.Small measuring tools:Ind.-
25,000
4.Pollution Control Equipment -
2,00,000
5.Bore well and raw water system, DG set with accessories -
15,00,000
6.Excise and sales tax electrification and installation charges @ 40% cost of machinery and equipment -
27,20,000
7.Cost of Jigs, Fixtures etc. L.S.
5,00,000
8.Cost of office equipment L.S.
5,00,000
Total plant and m/c cost
95,20,000
(iii) Preoperative expenses
5,00,000
Total Fixed Capital (i+ii+iii) Rs. 2,91,50,000 + 95,20,000 + 5,00,000
3,91,70,000
B. Working Capital (per month)
(i) Personnel
Description
No.
Salary
Total
(In Rs.)
i) Administrative and Supervisory
General Manager
1
30,000
30,000
Commercial Manager, Sales and Marketing staff, finance and accounts staff and purchase staff and stores staff
  
1,75,000
Administrative officer and staff
  
30,000
Production manager, laboratory chemists maintenance engineers and staff, shift incharges
  
2,00,000
Chowkidar/Watchman
7
 
21,000
ii) Technical
Skilled Workers
40
5000
2.00,000
Semi-skilled workers
45
4000
1,80,000
Un-skilled Workers
40
3000
1,20,000
Total
9,56,000
Add perquisites @ 22%
2,10,000
Total
11,68,000
(ii) Raw Materials
Sl. No.
Particulars
Ind./ Imp.
Qty.
Rate (Rs.)Amount (In Rs.)
1.
M.S. Channel 75 × 40 to × 50 mm
Ind.
9 MT
40,0003,60,000
2.
M.S. Equal Angle 25× 25×3 to 50×50×6 mm
Ind.
15 MT
40,0006,00,000
3.
M.S. Flat 50 to 70 mm wide
Ind.
3.750 MT
40,0001,50,000
4.
Aluminium chequered Plate 8 mm to ½ inch
Ind.
3 MT
2,50,0007,50,000
5.
CR/BP Sheet 10 to 26 SWG
Ind.
75 MT
52,00039,00,000
6.
M.S. Pipe 3/4" to 1" Dia
Ind.
1.500 MT
40,00060,000
7.
Aluminium Rolled Sections
Ind.
1.500 MT
2,50,0003,75,000
8.
Bought out items and hardware items
Ind.
L.S.
 2,00,000
9.
Other bought out items such as Raxine Ply,. PVC. Sheet. Foam OTC, Electrical fittings and fixtures, emblem etc.
Ind.
L..
 5,00,000
Total68,95,000

(iii) Utilities
Amount
(In Rs.)
Power150x0,8x0.73x24x25x42,10,000
WaterL.S.10,000
Total2,20,000

(iv) Other Contingent Expenses
Amt (In Rs.)
Lubricants
20,000
Postage and Stationery and communication expenses
30,000
Consumable stores (Redoxide, Paint, Putty, Kerosene, Emery paper, Welding electrode, tools etc.)
5,00,000
Transport Charges
25,000
Advertisement and Publicity
25,000
Insurance Charges
21,000
Sales Expenses
1,50,000
Misc. Expenses
50,000
Total
8,21,000

(v) Total Recurring Expenditure (per month)(In Rs.)
Staff and labour11,68,000
Raw material68,95,000
Utilities2,20,000
Other Contingent Expenses8,21,000
Total91,04,000

(vi) Working capital for 3 monthsRs. 2,71,35,000
C. Total Capital Investment
(i) Fixed CapitalRs. 3,91,70,000
(ii) Working Capital for 3 monthsRs. 2,73,12,000
TotalRs. 6,64,82,000
Machinery Utilisation
It is assumed that machinery will be utilised at 75% efficiency.
Financial Analysis
(1) Cost of Production (per year)
Amt (In Rs.)
Total recurring cost
10,92,48,000
Depreciation on building @ 5%
7,58,000
Depreciation on Dies, Jigs and Fixtures etc. @ 20%
1,00,000
Depreciation on machinery and equipments @ 10%
8,52,000
Depreciation on office equipment 20%
1,00,000
Interest on total capital investment @ 12%
79,78,000
Total11,90,36,000
(2) Turnover (per year)
Sl. No.Item
Qty.
Rate
(Rs.)
Total
(In Rs.)
i)Full size Bus body
324 Nos.
4,11,440 per piece
13,33,00,000
ii)Sale of scrap
90 MT
20000/MT
18,00,000
Total
13,51,00,000

(3) Net Profit (per year) (before tax)

=
Rs. 13,51,00,000 – 11,90,37,000
 =Rs. 1,60,63,000
 
(4) Profit Ratio
=
Net Profit (per year) ×100
--------------------
 
Total Sale
 
=
1,60,63,000 × 100
----------------------
 
13,51,00,000
 

=
11.89%
 
(5) Rate of Return
=
Net Profit (per year) × 100
--------------------------------
 
Total investment
 
=
1,60,63,000 × 100
-----------------------
 
6,64,82,000
   
=
24.16%
(6) Break-even Point
Fixed Cost(Rs.)
Depreciation on machinery and equipment, tools, fixtures, office equipment and building18,10,000
Interest on total investment79,57,000
40% of Salary and wages56,06,000
40% of utilities and other contingent expenses39,40,000
Total1,93,13,000

B.E.P=Fixed cost × 100
-----------------------
  Fixed cost + Profit
   
 =1,93,34,000×100
-------------------------------
  1,93,34,000 + 1,60,63,000
   
 =54.62%
Additional Information 

The unit should install degreasing and phospating plant for obtaining long life and good quality paint of bus body to improve the quality of product .

Addresses of Machinery and Equipment Suppliers 

1. M/s. Parekh Machine Tools
5, Khetra Das Lane, Behind Broad
Way Hotel, Kolkata.

2. M/s. Economic Machine Tools
21, Dr. V.B. Gandhi Marg,
(Forbes Street), Fort,
Mumbai-1

3. M/s. Master Engg. Works (Regd.)
G.T. Road (Dholewal), Opp. Indian
Oil Petrol Pump, Ludhiana-3.

4. M/s. International Machine Tools Corporation

5, Nyayamurti G.N. Vaidhya Marg,
Bank Street, Post Box No-2,
Behind State Bank of India,
Fort, Mumbai-1.

Raw Material Suppliers 

1. M/s. Steel Authority of India.
2. State Laghu Udyog Nigam.
3. Local Market.